Abergeldie collaborated with Hunter Water to deliver the Grahamstown Dam Stage 2 Augmentation project, which included the construction of a new spillway and embankment. Abergeldie built a new embankment dam, spillway, and outlet works to accommodate the increasing demand. This project raised the reservoir water level to RL 12.8, resulting in a 50% increase in storage capacity.
The scope of work included:
With a commitment to protecting the local ecosystem, the team constructed frog ponds north of the site to accommodate a local frog species. The new embankment construction required dewatering a significant portion of the lake. To ensure the preservation of aquatic life, fish and turtles were carefully relocated to the main body of the lake before these works began.
Abergeldie strategically planned to ensure that all water transfers were conscientiously managed, with 180,000,000L of water pumped back into Grahamstown Lake instead of being released through the existing spillway gates. A further 80,000,000L of acidic, low-pH water was treated and pumped into Grahamstown Lake.
The team effectively managed resources by repurposing materials throughout the project. They used 30,000m³ of surplus material to backfill an existing borrow pit near residents. Additionally, approximately 50,000m³ of acid sulphate soil was treated on-site and stockpiled for future use by Hunter Water in constructing a levee downstream of the new spillway.
A key objective of this project was the construction of a new spillway, designed to safely discharge flood flows from the dam. This critical infrastructure upgrade not only enhances the dam's capacity to manage excess water during heavy rainfall but also significantly improves overall safety and flood risk management for the surrounding communities.