Abergeldie was engaged by Sydney Water to deliver the Marsden Park Industrial Sewage Pump Station. This encompassed the construction and installation of mechanical and electrical equipment and the commissioning of the new sewage pump station. The works also involved connections to rising and gravity mains to serve the surrounding industrial precinct. The new industrial sewage pump station at Marsden Park now meets anticipated flow requirements, increasing from 8,362 EP in 2020 to 40,568 EP by 2030.
The scope of work included:
The site was prone to flooding during storm events, necessitating the removal of the levee on the downstream adjacent block before placing and compacting fill to raise the pump station above flood level.
The water table was identified at 3m below ground level, which posed a high risk of groundwater ingress through the alluvial material. Abergeldie used secant piling to stabilise the site and enable effective groundwater dewatering to address this.
Collaboration was central to the project, with scope, design, costs, and methodology continuously reviewed under the GC21 contract and the supplementary Collaborative Framework Agreement. This approach fostered an open register for identifying and managing project risks and opportunities, encouraging participation from all parties, including external stakeholders.
Abergeldie’s team worked closely with property owners, conducting face-to-face meetings throughout the construction of the new pressure main, which primarily involved open trench methods. This collaborative approach minimised disturbances, even when horizontal directional drilling under Eastern Creek required access through private properties to protect sensitive environmental features, such as road infrastructure, creek crossings, and heritage sites.